Pallet tenders are usually built to compare prices. That makes sense on paper, but the winning bid on price can easily cost more within a couple of quarters — and a typical tender document has no way of detecting it.
What a typical pallet RFP contains
Three things, usually: a volume, a footprint and a grade name. Sometimes a delivery expectation. Occasionally a sustainability questionnaire bolted on at the end, written by somebody who has not spoken to the person writing the specification.
That is enough to generate comparable prices and not nearly enough to generate comparable offers, for one specific reason.
Grade names are not standardised
There is no legally binding grading standard for used pallets in North America. Grade A means whatever the supplier selling it says it means, and at the boundaries — how many repairs, how much weathering, how far out of square — the definitions diverge by hundreds of pounds of racked capacity.
So a tender asking for "500 Grade A 48×40 per week, delivered" will produce bids that differ meaningfully on price and by considerably more on what actually arrives. The procurement process believes it is comparing like with like. It is not.
A tender specified by grade name is a tender specified in a language where every supplier has their own dictionary.
The three questions that separate suppliers
1. Will you supply your written grading standard?
Not a grade name. The document. A supplier who has one will send it immediately; a supplier who does not will send a paragraph about industry standards. Both answers are informative.
2. What happens to a repaired Grade A pallet?
If you could only ask one question, ask this. If the answer is that it stays Grade A because the repair is sound, the grade has stopped being a specification and become a sales category — and you will have to inspect every delivery, which destroys the efficiency grading exists to create. A supplier who re-grades repaired units downward is giving up some margin to keep the grade meaningful.
3. What is your credit or dispute rate?
The best question in the set, because it cannot be answered aspirationally. Either a supplier knows the number or they do not, and if they do not, that is the answer.
The number the tender should actually be scored on
All-in cost per trip: purchase plus repair plus freight plus disposal minus buy-back, divided by pallet movements. It is the only measure that captures every lever at once.
| Source | Typical contribution | Visible in a price-based tender? |
|---|---|---|
| Buying fewer units | Large | No |
| Eliminated disposal cost | Moderate | No |
| Reduced internal handling | Moderate | No |
| Buy-back credit | Moderate | No |
| Lower freight | Small | Partly |
| Lower unit price | Small | Yes |
| Less: repair spend and fees added | Negative | Yes, and it looks bad |
Read the right-hand column. A price-based tender can see only a small slice of the available benefit, and the lines it sees most clearly — repair spend and management fees — look like costs while actually being the mechanism.
Why a high repair spend is a good sign
Procurement instinct is to minimise it. But repair is what suppresses purchasing: an inexpensive companion board can buy several more trips, against the price of a whole replacement pallet.
If a tender response shows repair spend at zero and purchases halving, ask where the pallets came from. There is no third mechanism.
A scorecard that would find the right supplier
| Criterion | Priority | Evidence to require |
|---|---|---|
| Unit price, blended across your grade mix | High | Dated quote, freight shown separately |
| Grade reliability | High | The written standard, plus a credit-rate number |
| Repair capability | High | Throughput, repair ratio, or a site visit |
| Buy-back capability | Medium | How they price surplus, and a specimen sort sheet |
| Freight structure | Medium | Fleet access, backhaul, route frequency |
| Documentation and reporting | Medium | A specimen diversion summary |
| Service standard, measured | Lower | Last quarter's actual figures |
| Capability depth | Lower | ISPM-15 treatment access, custom builds, odd sizes |
Two things to do before the tender goes out
- Build the baseline. Purchase, repair, freight, disposal, handling, buy-back — on one page. Without it you cannot score anything except price.
- Measure your loss rate for three months. Four numbers a month: received, shipped, purchased, counted at month end. Measured loss is nearly always higher than people guess, which means many tenders are modelled on a fiction.
Key takeaways
- Grade names are not standardised, so a tender specified by grade name is not comparing like with like.
- Ask for the written grading standard, what happens to a repaired Grade A unit, and the supplier's credit rate.
- Score on all-in cost per trip. Unit price is only a small part of the available saving.
- A high repair spend is the mechanism, not the overhead. Zero repair spend plus halved purchases is not arithmetic.
- Build your baseline and measure your loss rate before the tender, or you will score on the only thing you can see.